石塑電梯門套的施工流程是什么?
石塑電梯門套是一種pvc+天然石粉組成的新型混合材質,這種材質的電梯套不但擁有大理石的花紋與質地,更擁有良好的韌性與硬度,可以說是一種性價比非常高的材質門套材料。那么,石塑電梯門套的施工流程是什么呢?
Stone plastic elevator door pocket is a new mixed material composed of pvc+natural stone powder. The elevator pocket made of this material not only has the pattern and texture of marble, but also has good toughness and hardness. It can be said that it is a kind of door pocket material with very high cost performance. So, what is the construction process of the stone elevator door pocket?
石塑電梯門套
Stone plastic elevator door pocket
1、物料籌備:線條、側板、泡棉膠、硅酮膠(或云石膠)、45°切割鋸、臺鋸、膠槍、紅外線儀器;
1. Material preparation: line, side panel, foam glue, silicone glue (or marble glue), 45 ° cutting saw, table saw, glue gun, infrared instrument;
2、布局墻體基面清算清潔外面沒有油污、浮塵、并查驗墻面平坦度和垂直度。超差部門應剔鑿或用水泥沙漿修補缺點,加固找平,方能施工;
2. The base surface of the layout wall shall be cleared and cleaned without oil stain and floating dust, and the flatness and perpendicularity of the wall shall be checked. The out of tolerance department shall chisel or repair the defects with cement mortar, reinforce and level before construction;
3、在墻面找出水平線、垂直控制線;
3. Find out the horizontal line and vertical control line on the wall;
4、切割鋸采納45度角對線條切割并對角拼接反省平坦度厚板+線條形式:假如墻面是干掛大理石根基,需要用小木方在墻面上找3-4個點,而后用云石膠點粘,小木方周圍用發(fā)泡膠添補;而后將切好45度切角的線條卡扣在側板上,線條另一側點粘到墻面上;薄板+線條形式:
4. The cutting saw adopts a 45 degree angle to cut the lines and make diagonal splicing to reflect on the flatness of the thick plate+line form: if the wall is a dry hanging marble foundation, you need to find 3-4 points on the wall with a small wooden square, and then stick them with marble glue, and use foam glue to fill around the small wooden square; Then snap the line with 45 ° chamfer on the side plate, and stick the point on the other side of the line to the wall; Sheet+line form:
假如墻面是干掛大理石根基,需要用細木工板打底,而后將薄板用泡棉膠暫時牢固,云石膠點粘到細木工板上;而后將薄板切割部門卡在線條卡槽中 ,將線條裝置到位,壓實,牢固在墻體細木工板基面上。卡槽一方面能夠遮擋住側板切割處的瑕疵,另一方面裝置速率能夠進步。(分外闡明:泡棉膠起到暫時牢固的感化,硅酮膠24小時內無奈凝結,但其前期感化力強,以是二者共同應用才能達到預期后果)
If the wall is dry hanging marble foundation, it needs to be bottomed with blockboard, and then the thin board is temporarily fixed with foam glue, and marble glue points are stuck to the blockboard; Then, clamp the thin plate cutting department in the line slot, put the line device in place, compact it, and firmly fix it on the base surface of the wall blockboard. On the one hand, the card slot can cover the defects at the cutting of the side panel, and on the other hand, the device speed can be improved. (It is particularly clarified that the foam adhesive has a temporary and firm effect, and the silicone adhesive cannot be coagulated within 24 hours, but its early effect is strong, so the expected consequences can be achieved only when both are used together.)
7、將對角處裂縫打硅酮膠填滿抹
7. Fill the diagonal cracks with silicone glue
8、將線條與墻的間隙打膠抹
8. Glue the gap between the line and the wall
9、側板依據現實尺寸用臺鋸切割,施工方法請參照線條(根基平坦,泡棉膠暫時牢固,硅酮膠點粘
9. The side plate shall be cut with a bench saw according to the actual size. For the construction method, please refer to the line (the foundation is flat, the foam glue is temporarily firm, and the silicone glue is stuck
以上就是為大家介紹的有關人工湖設計的詳細的介紹,希望對您有所幫助.如果您有什么疑問的話,歡迎聯系我們.我們將以的態(tài)度,為您提供服務http://caiaiwo.cn
The above is a detailed introduction to the design of the artificial lake. I hope it will be helpful to you. If you have any questions, please contact us. We will provide services for you with our attitude http://caiaiwo.cn
下一篇:電梯門套與電梯門套花色的關系上一篇:不銹鋼玻璃門的選購方法